A landmark infrastructure development project involving the four and six laning of the Hyderabad - Vijayawada section of NH-9 in Andhra Pradesh.
Successfully introduced a new methodology to arrest soil erosion in high embankment areas, ensuring long-term road stability and structural resilience.
Punj Lloyd is proud to deliver Sikkim’s first greenfield airport, providing vital air connectivity to this land-locked state. Built at Percheda Top, this project is a marvel of civil engineering.
Operational Altitude
One of the five highest airports in India upon completion.
One of the tallest reinforcement walls in the world, engineered to withstand hostile weather and deep valley gradients.
Maximum cast in a single month by any contractor.
Erected at M.G. Road Station in just 48 hours.
Extensive scope including construction of 8 Metro stations—from pile foundations and pier arms to complete architectural finishing, fire protection, and electronic systems.
Foundation: Largest and deepest pile cast executed among all site contractors.
Concrete: 672 Cum poured at Trinity Circle in 48 hours for basement raft & tank.
Steel: 1500 MT of in-house structural steel fabrication for permanent structures.
A critical segment of the Kallang Paya Lebar Expressway (KPE), the largest road project in Singapore. Jointly undertaken with Daewoo Engineering Construction Co Ltd, this project represents the pinnacle of urban tunneling technology.
Design, Construction & Completion of 1.64km Tunnel.
2 Interchanges, Pedestrian Bridges & Link ways.
"The largest and most complex road infrastructure project in Singapore's history."
Construction duration shortened through massive use of precast elements.
This monumental project involved the construction of two 500m long, 2-storey "finger" buildings and the complex renovation of the existing terminal structures—all executed within a high-security airport environment.
Work was carried out amidst ongoing airport operations under a security-tight environment with zero disruption to passenger flow.
Note: Sembawang E&C introduced innovative galvanized fish tail inserts for above-ceiling installation, significantly reducing labor costs.
Strategic execution for DMRC involving massive segmental construction and deep-foundation engineering in the heart of the capital.
High-precision Segmental Construction Method used for seamless elevated connectivity.
Supported by 1,200 large diameter bored piles, ensuring unmatched structural stability.
Bored piles reaching depths of 30 meters to anchor the elevated corridor securely.